The Town of Trumbull released a three-week road milling and paving schedule, starting Monday, April 28, through the week of May 12.
The tentative schedule could change and updates will be posted on Trumbull-ct.gov. Various sections of the roads will be closed at different times throughout the process and the town said it will work to keep disturbances to a minimum.
All school bus stops will remain in their current locations.
Roadway milling will start first, on the following roads:
• Madison Avenue (from Trumbull/Bridgeport Town line to the Bridge over Merritt Parkway)
• Madison Avenue (from Canoe Brook to Buck Hill Road)
• Red Fox Lane,
• Kingsbury Drive,
• Copper Kettle Road,
• North Stowe Place
• Northfield (from Kingsbury to Copper Kettle).
Upon completion of milling, the town will begin re-paving the roads. Road construction is anticipated to begin at 7 a.m. daily.
Underground utility improvements are also slated to continue in the Roosevel Drive area, for the following roads:
• Heavenly Lane
• Mohawk Drive
• Oxen Hill Rd
• Old Hollow
• Putting Green Rd
• Roosevelt Drive
For updates, visit Trumbull-ct.gov.