The Town of Trumbull has released its paving schedule for the weeks of June 13 and 20.
Construction is expected to start at 7 a.m. daily and some roads may be closed to thru traffic at different times throughout the process.
Week of June 13, 2016:
1) Installation of Topsoil and Seeding will continue on Nokomis Road, Zephyr, Magnolia and Clemens Ave (from Sunrise to Magnolia).
2) Top layer of asphalt may be installed on Nokomis Road, Zephyr, Magnolia and Clemens Ave (from Sunrise to Magnolia) – weather permitting.
3) Roadway grading will continue on Pequonnock Road, Alice place, Sunset Avenue, Burton Avenue, Hillside Avenue, Cypress Lane, Cedar Crest Road and a portion of Berkshire Avenue (from Sunset Ave. to Hillside Ave).
4) Drainage improvements will continue on Machalowski Road.
2) Roadway grading will continue on Pequonnock Road, Alice place, Sunset Avenue, Burton Avenue, Hillside Avenue, Cypress Lane, Cedar Crest Road and a portion of Berkshire Avenue (from Sunset Ave. to Hillside Ave).
3) First layer of asphalt installation will begin on Pequonnock Road, Alice place, Sunset Avenue, Burton Avenue, Hillside Avenue, Cypress Lane, Cedar Crest Road and a portion of Berkshire Avenue (from Sunset Ave. to Hillside Ave) weather permitting-.